LAHORE – Finally some sigh of relief for millions of Pakistani households and businesses, as the federal government is looking at options to open new Sui Gas connections ending years of waiting.
For Pakistanis, Sui gas remains the most affordable energy source for cooking and other purposes while 3.5 million applicants have been left waiting due to ban imposed amid limited supply.
Sources familiar with the development told Pakistan Observer that decision is under serious consideration by policymakers to address growing surplus of imported liquefied natural gas (LNG), and to protect existing gas infrastructure, and to fulfil LNG supply commitments. It is backed by Ministry of Finance, as proposal seeks to ease pressure on the country’s foreign exchange reserves, which have been strained by the high cost of LNG imports.
For the unversed, long-standing ban on new Sui Gas connections was first imposed in 2009, but was partially relaxed in 2015, and was again closed three year back. Applications have continued to pile up with the country’s two main gas providers: Sui Northern Gas Pipelines Limited (SNGPL) and Sui Southern Gas Company Limited (SSGCL).
As per available information more than 1Lac new gas connections are expected to be issued in fiscal year 2025–26. This move comes alongside structural reforms aimed at meeting International Monetary Fund (IMF) conditions.
For now, the potential revival of gas connections offers hope to millions of families and small businesses long awaiting a vital utility—and marks a significant shift in the country’s energy policy direction.
Sui Gas Chares
Oil and Gas Regulatory Authority (OGRA) has announced a significant increase in gas tariffs to recover costs, reduce subsidies, and curb circular debt. While per-unit rates for household users remain unchanged, fixed monthly charges have surged—rising by 50% for protected users and up to 200% for high-consumption households.
Guide for New Gas Connection
If SNGPL gas pipeline exists in front of your home and is operational, you can apply directly for a connection. If no gas pipeline is available in your street, you will need to apply for a network extension.
Get required application form from SNGPL Regional Office Or download it online from the official SNGPL website
Fill Out the Application Form
Fill the form in capital letters. Choose the correct form based on whether the gas network is available or not.
Required Documents
Submit your completed application form with the following:
-
CNIC (Computerized National Identity Card) copy
-
Property ownership proof (e.g., registry or other legal document)
-
Gas bill from your nearest neighbor
Site Visit
SNGPL representative will visit your house in due course (based on your turn) They will assess if it’s technically and operationally feasible to provide gas.
Get Proposal Letter / Demand Notice
If your application is approved You will receive a Proposal Letter (Demand Notice It will include: House Line Plan A list of approved installation contractors in your region
Sui Gas Connection Charges 2025
You need to pay Service Line Charges + Security Deposit, depending on your plot size:
Under 10 Marlas
Charge Type | Amount |
---|---|
Service Charges | Rs. 1,500 |
Security Fee | Rs. 4,500 |
Total | Rs. 6,000 |
Over 10 Marlas Premises
Charge Type | Amount |
---|---|
Service Charges | Rs. 3,000 |
Security Fee | Rs. 4,500 |
Total | Rs. 7,500 |